Playground Updates

Print
Press Enter to show all options, press Tab go to next option

 playground_banner 

Exciting news! Seven parks will be receiving updated playground equipment and shade structures. The updates follow the City's playground replacement schedule which is based on the age and condition of the equipment, as well as industry standards and compliance regulations.

Updates to the following parks are slated to commence in November 2017: 

  • Earthwalk Park
  • Abraham Lincoln Park (Lincoln)
  • Mountain View Park
  • Larry L. Maxam Park (Maxam)
  • Ralph Foy Park (Foy)
  • Verdugo Park
  • Vickroy Park

The work will begin at Earthwalk Park and will be completed at that park by early January 2018. The entire project is anticipated to be completed by July 2018.

Take a look at the design renderings below:

 Earthwalk Park (existing shade structures) 
 Playground update complete! 

 Earthwalk

 Earthwalk2

 

 Abraham Lincoln Park (existing shade structures)
 Playground closed for construction: early June to mid-July 2018*

 

 

 

 Mountain View Park
 Playground closed for construction: early February to late March 2018*

 MountainView

 MountainView2

 

 Larry L. Maxam Park (existing shade structures)
 Playground closed for construction: mid-June to mid-July 2018*

 Maxam

 Maxam2

 

 Ralph Foy Park
 Playground closed for construction:late March to late May 2018*

 Foy

 Foy2

 

 Verdugo Park
 Playground currently closed for construction: late December 2017 to early March 2018*

 Verdugo

 Verdugo2

 

 Vickroy Park
 Playground closed for construction: early April to mid-June 2018*

 

vickroy2

 

* Construction schedule subject to change. Please check back for updated time schedule.

For more information, please call City of Burbank Parks and Recreation at: 818.238.5300.

View Full Site