Exciting news! Seven parks are receiving updated playground equipment and shade structures. The updates follow the City's playground replacement schedule which is based on the age and condition of the equipment, as well as industry standards and compliance regulations.

Updates to the following parks are slated to commence in November 2017: 

  • Earthwalk Park - COMPLETE
  • Abraham Lincoln Park (Lincoln) - COMPLETE 
  • Mountain View Park - COMPLETE 
  • Larry L. Maxam Park (Maxam) - UPDATE IN PROGRESS
  • Ralph Foy Park (Foy) - COMPLETE
  • Verdugo Park - COMPLETE
  • Vickroy Park - COMPLETE

The entire project is anticipated to be completed by the end of summer.

Take a look at the design renderings below:

 Earthwalk Park (existing shade structures) 
 Playground update complete! 

 Earthwalk

 Earthwalk2

 

Abraham Lincoln Park (existing shade structures)
Playground update complete! 

 

 

 

 Mountain View Park
 Playground update complete!

 MountainView

 MountainView2

 

 Larry L. Maxam Park (existing shade structures)
 Playground closed for construction: mid-June to mid-August 2018*

 Maxam

 Maxam2

 

 Ralph Foy Park
 Playground update complete! 

 Foy

 Foy2

 

 Verdugo Park
 Playground update complete!

 Verdugo

 Verdugo2

 

 Vickroy Park
  Playground update complete!

 

vickroy2

 

Last Updated 7/3/2018
* Construction schedule subject to change. Please check back for updated time schedule.

For more information, please call City of Burbank Parks and Recreation at: 818.238.5300.