Public Works Current Construction Projects

Print
Press Enter to show all options, press Tab go to next option


FOR THE LATEST ON LONG-TERM CLOSURES AND DETOURS RELATED TO THE I-5 HOV PROJECT, PLEASE VISIT http://i-5info.com/ OR TOLL FREE AT (855) 454-6335.

18-19 PROPOSED STREETS FOR THE ROAD REPAIR & ACCOUNTABILITY ACT (SB 1)

PLANNED PUBLIC WORKS STREET PROJECTS

AT&T CONDUIT RELOCATION
AT&T is relocating a major conduit system in downtown Burbank along Orange Grove and Front Street to allow for Caltrans to reconstruct the Burbank Boulevard bridge crossing the I-5 Freeway. Conduit relocation work is now complete and the Final Phase is currently underway. Normal work hours are 7:00 a.m. to 4:30 p.m. Due to job site conditions, work hours may vary from the normal schedule. 

Update/Final Phase:  AT&T has completed 81% of the cable installation. Upon completion of the cable system, AT&T will splice approximately 20 large fiber and copper cables in order to transfer the working services of all customers, residents, and businesses to the new cable system (approximately 20 thousand splices). Delays have occurred due to the lack of material availability by the demand of natural disasters. AT&T is working diligently and as quickly as possible to have crews complete the project, including street restoration, in time for the upcoming Burbank Boulevard bridge improvements (Fall 2018).  To maintain public safety, traffic control will remain intact in order for crews to safely access maintenance holes for splicing. For additional project information, please contact the Public Works project manager, Ricardo Sanchez at (818) 238-3954 from 7:30 a.m. to 4:00 p.m. 

SAN FERNANDO BOULEVARD/BURBANK BOULEVARD INTERSECTION IMPROVEMENT
The Burbank/San Fernando Intersection Project has experienced construction delays due to unforeseen underground utility conflicts, as well as necessary adjustments for construction sequencing to maintain traffic flow. Intermittent lane closures will occur through 9/25/18 for street striping. The project is currently anticipated to be completed by mid-October 2018. Avoiding this intersection, if possible, is highly recommended. For additional information, please contact the Public Works project managers, Ricardo Sanchez or Anthony Roman at (818) 238-3915 from 7:30 a.m. to 4:00 p.m.

View Full Site